White Paper | Project-Centric Finance

At-Risk Work & LNTP:
Execution Before the Contract

How project-centric companies authorize, budget, execute, and integrate pre-contract work without destroying their cost baseline, margin visibility, or revenue recognition integrity.

Revelation Technologies LLC revtech.consulting March 2026

Executive Summary

Every project-centric company has felt the squeeze: the customer needs work to start now, but the contract isn't signed yet. Sometimes you get a Limited Notice to Proceed. Sometimes you just get a verbal commitment and a prayer. Either way, work happens before the money is officially on paper. The financial, operational, and accounting implications are real. This paper walks through the end-to-end lifecycle of pre-contract work execution: how to authorize it, how to budget it, how to run it, and how to fold it into the executed contract without creating a margin-destroying accounting mess. Whether the pre-contract spend eventually becomes billable or gets absorbed as cost of performance, you need a clean plan from day one.

Applicability

This Isn't a Niche Problem

Pre-contract work execution is a reality across every project-centric industry. If your company recognizes revenue over time against contracts or project agreements, this paper applies to you.

🏗️Construction & Engineering
🛰️Aerospace & Defense
💼Professional Services
⚙️Industrial Manufacturing
🔧Oil, Gas & Energy
🏛️Government Contracting
💻Technology & IT Services
🏥Healthcare Capital Projects

The specifics vary by industry and contract type, but the core challenge is universal: you're spending money before the contract that funds that spend is finalized. The accounting treatment, governance framework, and integration mechanics follow the same playbook.

Section 01

Understanding the Two Mechanisms

Pre-contract work falls into two distinct categories. They share a common problem, but carry different risk profiles, authorization levels, and financial treatment.

⚠️

At-Risk Work

Work performed by the contractor at their own financial risk, typically before contract award, with no formal customer authorization. The contractor bears 100% of the cost exposure. It's a strategic bet: you start early to hold schedule, protect the customer relationship, or maintain competitive position, knowing the spend may never be recoverable.

📋

Limited Notice to Proceed (LNTP)

A written authorization from the customer directing the contractor to begin a defined scope of work prior to full contract execution. The LNTP establishes a cost ceiling, a scope boundary, and a customer obligation to reimburse allowable costs incurred within those limits. It carries contractual weight.

Key Differences at a Glance
DimensionAt-Risk WorkLNTP
AuthorizationInternal management decisionWritten customer authorization
Cost Exposure100% contractor riskCustomer-funded up to ceiling
ScopeContractor-defined; discretionaryCustomer-defined; bounded
Cost CeilingInternal budget onlyNot-to-exceed (NTE) amount specified
Contractual StandingNo enforceable right to recoverBinding; creates a reimbursement obligation
Revenue RecognitionNo revenue until contract executedRevenue recognizable against LNTP performance
Typical DurationWeeks to months30–120 days (usually specified)
Risk Alert

At-risk work that never converts to a contract is a direct hit to your P&L. Every dollar of at-risk spend should be tracked with the same rigor as contracted work. The audit trail matters whether you recover the cost or not. Sloppy tracking creates problems in both directions: it makes recovery harder if the contract lands, and makes the write-off harder to defend if it doesn't.

Section 02

Work Authorization & Governance

Starting work before a contract is signed isn't just a financial decision. It's a governance decision. The authorization framework must be airtight. If things go sideways, the paper trail is the only thing between your CFO and a very bad quarter.

Internal Authorization Framework

Regardless of whether the work is at-risk or LNTP, you need a formal internal approval process. It is the single most important control in the pre-contract lifecycle.

  1. Business Case PreparationThe Project Manager documents the strategic rationale, scope of pre-contract work, estimated cost, risk mitigation plan, and the probability and timing of contract execution. This isn't a one-pager. It's a decision document that will be referenced if things go wrong.
  2. Financial Impact AssessmentFinance models the cash flow impact, cost recoverability scenarios (full recovery, partial, zero), and the effect on project margin, estimate at completion (EAC), and overhead absorption. For LNTP, this includes validating the NTE ceiling against the planned burn rate.
  3. Multi-Level ApprovalAt-risk work requires escalated approval. Typically VP/GM level for amounts under a defined threshold, and executive/CEO approval above it. LNTP work follows a similar path but with legal/contracts review of the LNTP instrument itself.
  4. Work Authorization Document (WAD) IssuanceA formal WAD is issued, specifying: authorized scope, budget ceiling, charge numbers, period of performance, and stop-work triggers. This becomes the control document for all subsequent cost accumulation.
  5. Stop-Work Criteria DefinitionPre-defined triggers that automatically halt pre-contract work: contract execution delayed beyond a target date, cost burn exceeds a threshold percentage of the ceiling, deal loss confirmed, or customer communicates material scope change. These must be written in the WAD, not in someone's head.
Authorization Flow
Step 1
Business Case
Prepared
Step 2
Finance
Assessment
Step 3
Exec / Legal
Approval
Step 4
WAD Issued &
Charge #s Open
Step 5
Work
Commences

LNTP-Specific Governance

When an LNTP is received, the Contracts or Legal team must validate several additional elements before work begins:

LNTP Validation Checklist

Scope alignment: Does the LNTP scope match the proposal scope, or is it a subset? Any delta must be documented and priced.

NTE ceiling adequacy: Is the authorized ceiling sufficient to cover the planned burn rate for the LNTP period? If not, the PM must re-scope or request a ceiling increase.

Terms flow-down: Do the LNTP terms reference the anticipated contract terms (liability, IP rights, insurance, warranties)? Gaps here create exposure at contract execution.

Period of performance: Is the LNTP duration realistic given the expected contract execution timeline? Build in buffer.

Section 03

Budgeting & Cost Structure

The budgeting approach for pre-contract work often gets treated as temporary, with lightweight tracking that creates problems downstream. When the contract executes, Finance is left reconciling two cost baselines into one coherent EAC. The better approach is to structure the budget and cost accumulation correctly from day one so that integration is a clean handoff, not a reconstruction project.

WBS & Charge Number Architecture

Pre-contract work must be tracked in a project structure that mirrors the anticipated contract WBS. Two reasons this matters: (1) clean integration at contract execution, and (2) audit readiness if the costs become billable or are reviewed by external auditors.

Recommended Project Structure for Pre-Contract Work
Program X (Top-Level Project)
├── X.PRE Pre-Contract / At-Risk Phase  Pre-Award
├── X.PRE.ENG Engineering / Design
├── X.PRE.PROC Long-Lead Procurement
├── X.PRE.PM Project Management
├── X.PRE.SUPPORT Tooling / Site Prep / Test Setup
├── X.01 Contract Phase 1 (Post-Execution)
├── X.01.ENG
├── X.01.PROC
├── ...
├── X.02 Contract Phase 2

The X.PRE structure allows all pre-contract costs to be accumulated in dedicated project elements that can later be either (a) reclassified into the contract project structure at execution, or (b) closed out and absorbed as period cost or allocated to cost of goods sold.

Budget Baseline: Two Scenarios

Scenario A: LNTP Budget

The budget baseline is the NTE ceiling from the LNTP instrument. The PM manages to this ceiling with the same rigor as a fully executed contract. Cost and schedule tracking must be formal, even if full earned value management is not required.

ASC 606 NTE Controls

Scenario B: At-Risk Budget

The budget is internally authorized via the WAD. It represents the maximum exposure the company is willing to absorb if the contract never materializes. This is effectively a pre-contract investment decision and should be governed with the same rigor as any capital allocation.

WAD Controls Internal Budget

Practical Guidance

Even for at-risk work, set up budgets by cost element: direct labor by skill mix, subcontractor, materials, travel, and other direct costs. If this work becomes billable, you'll need cost element detail to support invoicing and audit. If it doesn't become billable, you'll need it for accurate project post-mortem and overhead allocation.

Section 04

Execution & Cost Management

Once authorized, pre-contract work must be executed with the the same cost discipline as a signed contract. More, actually. The margin for error is thinner and the consequences of overrun are less forgiving.

Cost Accumulation Rules

  1. Dedicated Charge Numbers OnlyAll time, material, and expense charges go to the pre-contract project elements. No co-mingling with other projects, no "parking" costs on overhead accounts to be reclassified later. Auditors will find it. Your own Finance team will find it. Either way, it's a mess.
  2. Timekeeping DisciplineEmployees must charge directly to the pre-contract charge numbers from day one. Timecard approvals, supervisor reviews, and reconciliation processes apply identically to any active project.
  3. Weekly Cost Burn TrackingThe PM reviews actual vs. budget weekly. For at-risk work, if burn rate exceeds plan by more than 10%, stop-work evaluation triggers. For LNTP, approaching 80% of the NTE ceiling triggers a formal ceiling assessment and customer notification.
  4. Procurement & Subcontract Commitment ControlPurchase orders and subcontracts issued during the pre-contract phase carry extra risk. Cancellation clauses are mandatory. No long-lead material buys without explicit executive approval and contractual protections.
  5. Cost SegregationIf any pre-contract costs include elements that are non-billable by nature (entertainment, certain overhead allocations, costs outside the anticipated contract scope), they must be segregated immediately, not at contract execution time.
Pre-Contract Cost Management Cadence
Activity
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
At-Risk Execution
LNTP Period
Integration Window
Executed Contract
At-Risk LNTP Integration Executed Contract
Section 05

Contract Integration at Execution

Integration at contract execution is where the upfront discipline pays off. Without a planned transition path, Finance ends up reconciling two separate cost baselines into a single EAC after the fact. The integration approach should be defined before pre-contract work begins, not figured out after the contract is signed.

Integration Playbook

1. Cost Reconciliation & Validation

Reconcile all costs accumulated on the pre-contract project elements. Validate every charge against the WAD scope. Remove or reclassify any costs outside the authorized scope. Produce a clean incurred cost summary by cost element and project element.

2. Contract WBS Mapping

Map each pre-contract project element to its corresponding contract WBS element. This is a one-to-one or many-to-one mapping. Never one-to-many. Every pre-contract dollar must land in exactly one contract element. Traceability matters more than convenience.

3. EAC / Budget Baseline Reset

The contract's cost baseline must reflect the pre-contract actuals as "burned" budget. Earned value for completed pre-contract work is established at contract execution. Remaining budget is allocated to forward work. If pre-contract costs exceed the value allocated to that scope, you're already in a negative margin position. Surface it immediately.

4. Schedule Integration

Pre-contract activities become completed milestones in the project schedule. Successor activities and dependencies update. Critical path recalculated. Any schedule risk created during the pre-contract phase gets surfaced in the project risk register.

5. ERP System Cutover

In the ERP: pre-contract project elements are closed to new charges, actual costs are settled or reallocated to contract project elements via transactional postings, and the contract project is activated with full budget load. Cost element detail, commitment items, and billing plan assignments transfer cleanly. If the WBS was structured correctly upfront, these postings are straightforward. If not, you're looking at manual journal entries and reconciliation work.

ERP Best Practice

The cleanest approach is to create the pre-contract project as a child element of the anticipated contract project in the WBS hierarchy from day one. At contract execution, the pre-contract elements are statistically closed and their accumulated costs settled upward or laterally into the contract WBS. This preserves the audit trail, maintains general ledger integrity, and avoids manual journal entries to move costs between unrelated cost objects.

Section 06

Financial Outcomes: The Decision Tree

When the contract executes (or doesn't), the at-risk costs face one of three outcomes. The financial treatment is different for each, and the accounting must be determined before the books close for the period in which the contract executes.

At-Risk Cost Resolution Decision Tree
Pre-Contract Costs Incurred
Contract Executed?
Yes: Executed
Costs Negotiated as Billable?
Yes
Costs integrate into contract WBS. Revenue recognized per ASC 606 over performance obligation. Full cost recovery.
No
Costs absorbed into contract EAC as cost-to-complete. Reduces margin. Recognized in COGS / WIP during revenue recognition against the performance obligation.
No: Deal Lost
Costs expensed as business development / pre-contract cost. Hits P&L as period expense. No revenue. No recovery.

Outcome A: At-Risk Costs Become Billable

Best case. During contract negotiations, the contractor successfully argues that the pre-contract work was performed at the customer's direction (implicit or explicit) and should be included in the contract value. The pre-contract costs reclassify from the pre-contract WBS to the contract WBS. Revenue is recognized under ASC 606 as part of the overall performance obligation. The EAC reflects these costs as incurred with corresponding budget allocation.

Outcome B: At-Risk Costs Absorbed into Contract

More common. The customer won't pay for the at-risk work separately, but the contract executes. The contractor absorbs the at-risk costs as part of their cost of performance:

Illustrative Journal Entries: At-Risk Cost Integration (Non-Billable)
Account
Debit
Credit
At contract execution, reclassify to contract WIP:
WIP, Contract X (Contract WBS)
$450,000
WIP, Pre-Contract (At-Risk WBS)
$450,000
Revenue recognition: costs flow through COGS:
COGS, Contract X
$450,000
WIP, Contract X
$450,000

Under ASC 606, the at-risk costs become part of the total estimated cost at completion. They reduce the margin on the contract but are recognized proportionally as the performance obligation is satisfied over time (cost-to-cost input method). These costs were incurred before the contract, but they contribute to satisfying the performance obligation and therefore must be included in the EAC used for percentage-of-completion calculations.

Outcome C: No Contract Executed

Worst case. No contract, no recovery. The at-risk costs are expensed in the period as business development, pre-contract, or bid and proposal expense. It's a direct P&L hit. If the company allocates these costs to an overhead pool, it increases the overhead rate, which flows to all active projects. Double hit: direct cost lost, and indirect rates go up.

Audit Sensitivity

The decision to capitalize at-risk costs as WIP (versus expensing immediately) requires a probability assessment that must be documented. Auditors will scrutinize the basis for concluding that contract execution was "probable." Contemporaneous documentation of the probability assessment is essential. That means documenting the competitive landscape, customer communications, and deal status. Retroactive justification does not pass muster.

Section 07

LNTP Integration: A Cleaner Path

LNTP integration is mechanically simpler because the costs are already customer-authorized and the accounting treatment is established from day one. But "simpler" doesn't mean "automatic."

  1. Validate LNTP Scope → Contract Scope AlignmentConfirm that every LNTP deliverable maps to a contract line item. Any LNTP work that falls outside the executed contract scope becomes a negotiation item and potentially unrecoverable.
  2. Cost SettlementLNTP costs settle into the contract WBS at their actual incurred value. No markup, no adjustment, unless the LNTP instrument specifies fee accrual, which is rare pre-execution.
  3. Fee / Margin CalculationFee on LNTP costs is typically calculated and applied at contract execution. The contract price includes the LNTP costs plus applicable fee, established during the contract negotiation. The contractor's margin on LNTP work is determined retroactively.
  4. Billing TransitionIf the LNTP authorized interim invoicing, reconcile all LNTP billings against the executed contract. Adjust as needed. If no interim billing was authorized, the LNTP costs become part of the first billing cycle post-execution.
Section 08

Revenue Recognition Under ASC 606

Revenue recognition for pre-contract work intersects with ASC 606 in ways that require careful judgment. The core question: when does a performance obligation exist, and how do pre-contract costs relate to it?

LNTP Revenue Recognition

An LNTP creates a performance obligation from the date of issuance. Revenue is recognized over time using the cost-to-cost input method, where progress is measured by costs incurred relative to total estimated costs for the LNTP scope. At contract execution, the LNTP performance obligation merges into the broader contract performance obligation, and the cumulative catch-up adjustment (if any) is recorded.

At-Risk Revenue Recognition

At-risk work creates no performance obligation until the contract executes. No revenue is recognized during the at-risk period. Costs are capitalized as WIP if recovery is probable (i.e., the contract is expected to execute), or expensed immediately if recovery is not probable.

ASC 606 Treatment by Outcome
OutcomeRevenue ImpactCost TreatmentMargin Impact
Costs become billableIncluded in transaction price; recognized over time via cost-to-costReclassified to contract WBS; part of EACNeutral (if priced at cost + margin)
Costs absorbed (non-billable)No incremental revenue; total transaction price unchangedAdded to EAC; increases total cost at completionNegative: margin compression
No contract executedNo revenue recognizedExpensed as period costDirect P&L hit; potential overhead rate increase
Section 09

ERP System Considerations

Your ERP must support the full lifecycle: pre-contract cost accumulation, segregation, integration, and ongoing contract execution. Here's what matters in practice.

ERP Configuration Requirements by Phase
PhaseConfiguration RequirementERP Module
Pre-Contract SetupDedicated project/WBS with pre-contract status flag; budget profile with NTE controls; separate cost centers if indirect at-riskProject System Controlling
Cost AccumulationTime entry integration; commitment management for POs and subcontracts; real-time cost reporting against WAD budgetTime Mgmt Procurement
LNTP BillingMilestone or cost-reimbursable billing configuration; billing plan tied to LNTP NTE; rate applicationBilling Rev Acctg
Contract IntegrationSettlement rules from pre-contract to contract WBS; cost reclassification entries; budget reprogrammingProject System Finance
Post-ExecutionFull project controls structure; revenue recognition events; cost baseline with pre-contract actuals incorporatedProject System Rev Acctg
Section 10

Risk Mitigation & Best Practices

Pre-contract work is inherently risky. The companies who do it well share common disciplines.

  1. Treat Pre-Contract Like a ContractWAD, budget, charge numbers, cost reviews, stop-work triggers. If you wouldn't run a $5M contract without these controls, don't run $500K of at-risk work without them either.
  2. Document Everything in Real TimeCustomer direction (even informal), internal approvals, scope changes, cost status. If your auditor asks "why did you incur this cost?", the answer needs to exist in writing, dated before the cost was incurred.
  3. Build the Contract WBS FirstDesign the pre-contract project structure as a subset of the anticipated contract WBS. When the contract executes, the settlement postings and budget transfers should follow a predictable path, not require a forensic accounting exercise.
  4. Separate At-Risk from LNTP CostsEven if both are happening concurrently on the same project, they have different authorization levels, different cost recovery profiles, and different accounting treatment. Never co-mingle.
  5. Set Hard Limits and Honor ThemThe WAD ceiling is not aspirational. When you hit 90% of the at-risk budget, you stop and re-evaluate. The PM who says "just one more week" is the PM who blows the budget by 40%.
  6. Negotiate Retroactive Billing EarlyDon't wait until contract execution to raise the question of at-risk cost recovery. Build it into your negotiation strategy from the proposal phase. The earlier the customer acknowledges the pre-contract investment, the stronger your position at the table.
  7. Maintain Accounting ConsistencyPre-contract costs must be accumulated consistent with your established cost accounting practices. Changing your methodology mid-stream creates audit exposure and undermines the credibility of your cost data at integration.
Conclusion

The Bottom Line

Pre-contract work isn't going away. Customer timelines will continue to outpace procurement cycles, and contractors will continue to start work before the ink is dry. That's the reality of project-centric business.

The question isn't whether you'll do at-risk or LNTP work. It's whether you'll do it with the financial discipline, governance rigor, and system architecture to protect your company when the contract executes, and when it doesn't.

Set up the controls. Build the WBS right. Track the costs like they matter. Because they do.

About Revelation Technologies

Revelation Technologies (RevTech) is an SAP consulting firm specializing in project-centric industries including Aerospace & Defense, Government Contracting, Construction, Engineering, and Professional Services. We help companies design and implement the ERP architectures, financial controls, and project management frameworks that make complex project execution, including pre-contract work, operationally clean and audit-ready. Learn more at revtech.consulting.